The Knolls


Progress

The first view of the property.
June 2003
The first view from the street of the property located at 221A Richmond Street  in Sandhurst. It is a five acre parcel with 363 feet of shoreline frontage, with sandy beach (small and comes and goes with the wave action) and pebbles, stones, and boulders. The water is not visible through the undergrowth.
Michael at the road entrance with part of the municipal number.
July 2003
Michael and part of the street number sign.
Undergrowth and trees along the shoreline.
June 2003
The shoreline is wildly overgrown with underbrush and willows and ash trees. The trees were in strong competition with each other, and needed to be thinned out to provide room for the important ones to thrive, and to provide a view of the water, which is almost totally obscured.
In the brush.
July 2003
Diane in the foliage at the east end of the shoreline. This is what the brush and undergrowth was like before it was cleared out.
Diane as Jane.
August 2003
Exultant Diane, by the large willow, with some of the wood from the cleared trees.
The cleared shore from the land side.
August 2003
An arborist ("A Cut Above") was engaged to clear the underbrush, thin the trees, and trim the remaining trees. This was a huge job as there were large fallen willow trunks in several places. The view of the water looks to the Western Gap between Amherst Island and the eastern end of Prince Edward County.
Clearing up the rubbish.
August 2003
There was a lot of rubbish in the undergrowth, mostly from the cottage that was on the earlier severed lot, and at sometime in the past had been cleared off the property, and precipitating the return of this parcel to the larger one.
The cleared shoreline from the water side.
August 2003
From the kayaks it was possible to appreciate the topography of the property from the water. It is possible to see that the central portion of the shoreline is bracketed by a section at either end left as a buffer with the neighbouring properties.
The section of the shore with boulders running into the water. The water is low.
August 2003
Adjacent to the "sandy" beach where the kayaks are launched is this spread of granite glacial boulders running out into the water. Opposite the eastern end of Prince Edward County is visible with a part of the Western Gap.
A view along the shore looking east.
August 2003
The willows follow the stony shore berm, providing shade. Looking to the east.
The big knoll.
August 2003
The property has three or four knolls, that make it rather distinctive in relation to the surrounding landscape which is quite flat. Hence the name Sandhurst, with "hurst" meaning "hillock". These are the only hillocks in the immediate area.
View to the north with the church.
November 2003
View of the Anglican Church on Bath Road from the small knoll.
Entrance road.
July 2004
The road into the building site take you over the top of the big knoll, seen above. The contractor for the road, septic bed, etc. is George Benn and Sons.
The end of the road where the house will be located.
July 2004
The end of the road where the house will be sited.
Looking to the shore from the end of the road.
July 2004
The road from the top of the big knoll, looking towards the shoreline.
The well is a shoreline well, prepared by blasting.
July 2004
Making the shorewell by blasting. Contractor Frank's Drilling and Blasting, Newburgh.
Shorewell tile.
July 2004
The shorewell. 
There is a path from the front of the house to the shore and then parallel to the shore line
October 2004
The path parallel to the shoreline. It can be approached from the front of the house.
Placing the gravel bed for the floor.
November 2004
Preparing the bed for the hydronic floor. Contractors are Wemp and Smith.
Compacting and levelling the gravel bed for the floor.
November 2004
Levelling the bed for the hydronic floor.
The septic bed.
November 2004
The tile bed for the septic system.
Making the septic bed.
November 2004
Dressing the tile bed for the septic system.
View of the house site from the top of the big knoll.
November 2004
A view of the house site from the top of the big knoll.
The forms for the footings.
November 2004
The form work for the footings seen at the garage entrance.
Placing the plumbing lines under the floor.
November 2004
Temporary plumbing!
Placing the plumbing runs under the floor.
November 2004
Placing the plumbing lines under the floor.
Placing the plumbing under the floor.
November 2004
The plumbing contractor is Brunet of Kingston.
View  from the top of the big knoll.
November 2004
A view of the site with the footing forms in place from top of the big knoll.
The trench for the waterline.November 2004 The trench for the waterline from the house to the shorewell.
The waterline and new grass at the path.
November 2004
The waterline with a view of the path with the germinating grass.
The  hydro trench.
November 2004
The trench for the hydro service. At the far end the excavator encountered a spring that would have served for a well!!
Diane pacing out the measurements.
November 2004
Diane pacing out the measurements.
One of the seedlings planted in the spring.
November 2004
One of the pine seedlings planted in the spring. The oaks, larches and pines seem to have had a good start in the cool and moist summer.
View of the site from the shoreline.
November 2004
A view of the house site from the shoreline. Follow the path.
Insulating the floor.
November 2004
The floor insulation ready to be installed.
Insulating the floor.
November 2004
Installing the floor insulation.
Insulating the floor.
November 2004
Is it really a puzzle?
The under floor insulation complete.
November 2004
The reinforcing mesh was placed November 11.
Placing the in-floor heating tubing.
November 2004
The hydronic floor heating relies upon loops of tubing in the concrete floor. McKeown  and Wood are the contractors.
Placing the in-floor heating tubing.
November 2004
This was a warmer, sunny day, so warm that the installers were remarking on how hot it was getting by 11 a.m., although the previous evening the temperature went down to -9 C.
Placing the in-floor heating tubing.
November 2004
When this stage is completed, the floor is ready to be poured along with the footings. The footings are "warm," which avoids the need for deep frost walls.
Pouring the footings and floor.
November 2004
The footings and floor being poured. The crew started at 7 a.m. intending to work into the evening if necessary to finish the surface.
Pouring the footings and floor.
November 2004
The footings and floor used about 50 cubic yards of concrete.
Pouring the footings and floor.
November 2004
Pouring the footings and floor. The main house area is complete.  The garage is still to be done.
The slab set..
November 2004
Two days after the slab was poured, the forms are stripped off in preparation for the application of rigid insulation along the edges. It had rained overnight, and the pools of water show that the slab is quite level, but not perfect. This is a view from the garage entrance.
Cutting the slab.
November 2004
It seems odd to "cut" the slab after so much trouble has been taken to get a smooth surface. It is assumed that all massive floors of concrete will want to crack somewhere. By cutting the slab surface to a depth of about one inch, the cracking will be directed along the weak points established by the cuts. However, it may never crack! This is a preventative measure to direct unsightly cracks in an orderly way.
Laying the conduit in the hydro trench.
November 2004
The hydro line will be underground. This seemed a good idea until a spring was discovered near the pole. Nevertheless, Hydro One said to proceed as planned in the layout (Plans).
Insulating the perimeter of the slab.
November 2004
The perimeter of the slab is insulated with "PolyVert," a 'greener' form of rigid insulation. The choices of material throughout lean to the sustainable, green category. The perimeter drainage is visible in this photograph, and will be covered with gravel and sand.
Nudera forms set in place.
November 2004
The Insulated Concrete Form (ICF) system selected for the walls is the Nudera product. It was selected because Nudera promoted an integrated building system, including floor and ceiling insulation systems. The latter proved to be too expensive compared to conventional insulation. Nevertheless, the wall system is very efficient and easy to put up to receive the concrete.
Nudera forms set in place.
November 2004
The placement of the exterior walls defines the interior space in a dramatic way.
Nudera forms set in place.
November 2004
The Nudera forms are unique in that they are somewhat like an accordion, and fold up for shipping, and unfold for installation.
View from the shore of the wall forms
November 2004
A view from the shoreline of the concrete forms being put in place. The previous two days were too rainy and windy to work on the site.
The walls two days later.
November 2004
A view from the south-west of the wall forms approaching their maximum height.
A close up of the west wall.
November 2004
A close up of the west wall and a window cut-out. The windows are close to the floor and life-size so from the inside it will seem possible to move out on the same level (but of course it is a window!).
Wall forms at their full height.
November 30, 2004
From the garage entrance, walls at full height.
East wall at full height.
November 30, 2004
From the east end, walls at the full height.
Front elevation from the shore path.
November 30, 2004
From the south-east, walls almost at full height.
Facade from the shore path.
November 30, 2004
Facade from the shore, walls partially completed to full  height.
The facade from the beach.
November 30, 2004
View from the sandy beach.
Facade from the shore.
November 30, 2004
View from the shoreline.
Shoreline to the east in November: low water
November 30, 2004
Looking east on the shoreline, low water.
Shoreline to the west: low water in No
November 30, 2004
Looking west on the shoreline, low water.
>>>>>>>>>>>>
>>>>>>>>>>>>
Go to December Progress  
To go to the March page.  


Home
Location The History The Plans The Progress Links
Webmaster: oneATbellonart.net (replace the AT with @)  <<<<<>>>>>  Last Updated May 1, 2005